New Changes to the Building and Construction Industry: Key Amendments to the Victorian Building Legislation and Regulations

KPA Lawyers | Melbourne
27 November 2025  ·  6 min read

KPA Lawyers | Melbourne

New changes to the Building and Construction Industry: Key amendments to the Victorian Building Legislation and Regulations


Building Legislation Amendment (Buyer Protections) Act 2025

Significant reforms to Victoria’s domestic building legislation have taken into effect from 1 July 2025 under the Building Legislation Amendment (Buyer Protections) Act 2025 (Vic) (Buyer Protections Act). This legislation aims to enhance consumer protections and improve regulatory efficiency.

The Buyer Protections Act establishes the Building and Plumbing Commission (BPC), which consolidates the functions of the regulators:

  • Domestic Building Dispute Resolution Victoria (DBDRV).
  • Victorian Building Authority (VBA); and
  • Victorian Managed Insurance Authority (VMIA).

The BPC is designed to minimise administrative delays and provide a unified approach to regulation within the building industry.

In this article, we will provide an overview of the key changes to the building regulations and legislation and will explain the new functions of the BPC.

Issuing occupancy permits

The Act introduces new preconditions applicable to developers that must be complied with before they can apply for an occupancy permit.

Developers will be required to notify the BPC of their intention to apply for an occupancy permit six to twelve months in advance of applying, in order to allow for an inspection to be carried out by the BPC.

Upon inspection, if a serious defect is found and if the BPC makes a rectification order, the developer will not be able to:

  • apply for an occupancy permit;
  • register a proposed plan of subdivision; or
  • complete an off-the-plan sale of the building,

until the rectification order is complied with.

The BPC may apply to VCAT for an extension of time, beyond ten years, in which it may issue a rectification order.

Rectification Orders – effective 1 July 2026

The BPC will have the power to issue a ‘Rectification Order’ (RO) to builders or developer to:

  • Complete incomplete building works;
  • Rectify defective and or non-compliant works; and/or
  • Fix consequential damage.

These powers allow orders against builders and developers for defective, incomplete or non-compliant work for up to 10 years after issue of occupancy certificate or practical completion.

A builder will be required to complete the works specified in the RO by the specified due date, typically at their own expense. Non-compliance may result in financial penalties, disciplinary action such as suspension of registration, or costs being recovered for completion of the rectification work by another builder.

A builder must ensure they promptly address and comply with a RO by the specified due date to avoid enforcement actions by the BPC. However, a builder may apply to the Victorian Civil and Administrative Tribunal (VCAT) for a review of the issuance of a RO.

If you receive an RO and require assistance on compliance and to understand your legal rights, please contact our office to discuss.

First Resort Statutory Insurance Scheme – effective from 1 July 2026

The new Statutory Insurance Scheme will be a “first resort insurance” product, enabling homeowners to make claims while the builder is still trading. This scheme covers losses arising or in connection with building work that is incomplete, defective or non-compliant.

The scheme aims to support consumers, with previously only being able to make a claim when the builder is deceased, becomes insolvent or has disappeared. Under this new framework, consumers will receive better coverage, including protection for lost deposits and earlier recourse to address defective building works.

New Developer Bond Regime – effective from 1 July 2026

Developers of residential apartments over 3 stories will soon be required to lodge a bond of 2% of the ‘total build cost’ with the BPC before applying for an occupancy permit.

Total build cost has been defined under the Buyer Protections Act as the estimated total cost of the building work carried out for or in connection with the construction of the residential apartment building.

The developer bond provides security to ensure any defective building works identified open completion of the works can be rectified and will be held by the BPC for 2 years following the issuance of an occupancy permit.

Domestic Building Contracts Amendment Act 2025 – effective from 1 December 2026

The Domestic Building Contracts Amendment Act 2025 (Vic) (Amendment Act) enacted on 11 September 2025 and are due to come into effect from 1 December 2026. This legislation introduces significant changes to the Domestic Building Contract Act 1995 (DBC Act), impacting domestic building contracts, obligations of builders and developers and consumer protections.

Key new provisions under the Amendment Act include:

  • Defining who qualifies as a ‘developer’ and limitations on the application of consumer protection measures in contracts between developers and builders.
  • The exclusion of the preparation of plans, specifications and bills of qualities from the definition of ‘domestic building work’. These services may be provided under preliminary service agreements and will not be covered by domestic building insurance.
  • Amendments to to deposit and progress payment requirements, especially in contracts involving significant off-sit constructions.
  • Allowance of cost escalation clauses only under specific circumstances:
  • contract price being $1million or more;
  • cost escalation in aggregate capped at 5% of the total contract price;
  • builders must provide written notice to the owner; and
  • the owner signs or initials the cost escalation clause.

Securities of Payment Act 2002 – effective from 1 September 2026

Under the Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Act 2025 (Vic), significant reforms have been introduced to the Building and Construction Industry Security of Payment Act 2002 (Vic) (SOPA). These amendments aim to enhance the efficiency of the payment claim process and affects both claimants and respondents.

Key changes include, but are not limited to:

  • Payment claims to be made on the last day of the month, unless dated earlier in a contract;
  • Default payment terms to be 10 days if there is no reference in a contract or limited to 20 days if stated.
  • Changes to how payments and claims are to be addressed during the Christmas shutdown period.
  • Improving lodgement options.
  • Changes to how the adjudication process is administered.

Should you require any assistance regarding the matters set out in this article, please do not hesitate in contacting our office to discuss.

The KPA Lawyers Media articles aim to keep our readers informed with regular updates regarding legal developments. It is not to be taken as legal advice. Liability limited by a scheme approved under Professional Standards Legislation.

SHARE THIS ARTICLE

The information contained in this article is of a general nature only and does not constitute legal advice. It has been prepared by KPA Lawyers without considering your specific objectives, circumstances or needs, and should not be relied on as a substitute for tailored legal advice.

While KPA Lawyers takes reasonable care to ensure that the information is accurate and current at the time of publication, we do not warrant its accuracy, completeness or currency and the law may change after the publication date. You should obtain legal advice from a lawyer before acting or relying on any information in this article.

Accessing or reading this article does not create a solicitor-client relationship with KPA Lawyers. To the fullest extent permitted by law, KPA Lawyers, its principals and employees disclaim all liability for any loss or damage arising from reliance on the information contained in this article. Liability is limited by a scheme approved under professional standards legislation.

This article was last updated on

GET IN TOUCH

Considering selling or buying a business? Speak directly with our M&A team — no obligation.


17 Sep 2026

Lost Capacity and No Enduring Power of Attorney? Your Options in Victoria

Failing to establish an Enduring Power of Attorney (EPOA) before losing decision-making capacity can lead to significant complications. Without an…

15 Sep 2026

BUSINESS SUCCESSION PLANNING: WHO TAKES CONTROL IF YOU CAN’T?

Many Australian business owners lack plans for incapacity or death, risking their families and businesses. Leon McPaul discusses the importance…

10 Sep 2026

WHAT DOES “HELD ON TRUST” MEAN IN A WILL?

The article clarifies the difference between holding assets “on trust” and having assets “in a trust” in the context of…

9 Sep 2026

When Does a Foreign Buyer Need FIRB Approval in Australia?

The FIRB position needs to be settled at the start of a transaction not after the deal is agreed. Foreign…

4 Sep 2026

VENDOR FINANCE IN A BUSINESS OR SHARE SALE: RISKS FOR VENDORS

Vendor finance can offer benefits in business sales, but also presents significant risks for the vendor. Key considerations include repayment…

3 Sep 2026

HOW LONG DOES ESTATE ADMINISTRATION TAKE IN VICTORIA?

The timeline for administering an estate varies widely, typically taking six months to several years depending on complexity. Executors have…

28 Aug 2026

WHICH ASSETS FORM PART OF AN ESTATE?

What your Will does and Doesn’t Control: Estate and Non-Estate Assets Explained When a loved one passes away, one of…

18 Aug 2026

GENUINE REDUNDANCY: A COMPLIANT PROCESS FOR EMPLOYERS

Many business owners face the challenging decision of making one or several roles redundant. Often, the decision is motivated by…

13 Aug 2026

EXECUTOR DUTIES AND RISKS: WHAT YOU NEED TO KNOW

An Executor can be held personally liable for mistakes during estate administration, including premature distribution and unpaid debts. Key responsibilities…


Stay Informed

Legal insights, delivered to your inbox

Subscribe to KPA Insights for practical legal guidance on property, family, employment and business law across Victoria , written in plain English, without the jargon.

Discover more from KPA Lawyers Melbourne | Expert Commercial, Estate, Property, Family & Litigation Law

Subscribe now to keep reading and get access to the full archive.

Continue reading